Vendors often quote 6 to 12 weeks to build an ePRO system. The build itself can take less than a week. What decides whether you are ready for first patient in is everything around it, and how the parallel work streams depend on each other.

ePRO trials rarely go wrong on the screens. They go wrong on timing: decisions taken too late, steps nobody owns, and a critical path that runs through translations and submissions, not the build. Today we are releasing two free references that show the whole picture. Both are a first look at our upcoming course, Managing ePRO (C07).

Two references, two zoom levels

  • The whole journey
    From the first protocol decision to the day the system is switched off: four stages and 36 steps, on two pages.
  • The critical stretch
    The 22 weeks from vendor contracted to first patient in, as three parallel lanes and the dependencies between them.

Reference 1: The ePRO timeline, end to end

Four stages, 36 steps, and a typical timeline.

Page one shows all 36 steps, grouped in four stages. Each step shows who is involved (sponsor, CRO, ePRO vendor or site) and its typical timing. Page two shows a typical timeline for a fictional, mid-complexity Phase III trial, ADV-302: a daily home diary, 9 countries, 14 languages and around 420 patients, with the key milestones from protocol final to decommissioning. Walk through the steps at protocol stage and ask which apply to your trial, and who owns each one.

  1. Decide and design
    Protocol development to protocol final.
  2. Source and contract
    Overlaps late protocol development, up to vendor contracted.
  3. Build and prepare
    Vendor contracted to go-live.
  4. Run and close
    Go-live to decommissioning.

ADV-302 in numbers (typical)

  • Protocol final to go-live: about 30 weeks
  • Vendor contracted to go-live: about 22 weeks
  • Recruitment: about 12 months
  • Last patient last visit to database lock: about 8 weeks
  • Database lock to decommissioning: about 3 months

Reference 2: ePRO build and prepare, in detail

The 22 weeks from vendor contracted to first patient in: three parallel lanes and the dependencies between them.

One page, three lanes, and the critical path for ADV-302. Most delays come from the dependencies between the lanes, not from any one step.

  1. Lane A: System and data
    Specification, build, testing, integrations, monitoring plan and data change process.
  2. Lane B: Instrument and content
    Licensing, electronic migration if required, and translations, priority languages first.
  3. Lane C: Readiness
    Submission material, CTA and EC/IRB, devices, help desk, and training for the investigator meeting and site initiation visits.

Plan to the real deadline

  • The real deadline is not a finished English test. It is everything needed for submissions, training and go-live.
  • Map your own country requirements: which need final local-language screens in the submission?
  • Agree review turnarounds, both ways, as milestones with named back-ups.

How to use them

Use the timeline as a checklist and a back-planning aid. Back-plan from your hard dates: submissions, investigator meeting, site initiation visits and first patient in. Then use both references with your CRO and ePRO vendor to agree one plan and close the gaps between you. The steps are the same in most ePRO trials. What differs is which apply, who owns them, and how early you start. Print them A4 landscape, or keep them open beside your plan.

What comes next

Both references are a free preview of Managing ePRO (C07), our upcoming course in TriTiCon Knowledgeworld. The full module follows ADV-302 through all four stages, with a step card for every step: when it applies, what to consider and decide, the classic pitfalls, and key regulatory guidance. It is coming soon.

In the meantime, the references stand on their own. Download them, put them in front of your team and your vendor, and see where the gaps are.

Download the references

Both are free, and free to share with attribution.

Reference 1: ePRO timeline, end to end Reference 2: ePRO build and prepare

More free resources: triticon.com/pages/resources · triticon.com

Educational content only. ADV-302 is a fictional trial and all timings are typical and indicative; yours will differ. Subject to change.

Connected to this article

Put the knowledge to work.

Explore the subject in a course

Try the teaching

Start with the free sample.

Explore selected lessons before choosing your course.

Explore the free course ↗
Related reading

Keep exploring.